Johnson Range
A near term open-pit gold project

Johnson Range is located approximately 170km north of Southern Cross and 6km northwest of the historical Evanston Mine. The project covers approximately 6km² of granted tenure and includes the historically mined Gwendolyn gold deposit.
The May 2026 JORC compliant Mineral Resource Estimate totals 2.041 million tonnes at 1.99g/t Au for 130,730 ounces of gold and includes an existing surface stockpile. The update represented a 26% increase in contained gold ounces from the previous estimate.
The September 2026 Pre-Feasibility Study established a Probable Ore Reserve of 308,000 tonnes at 2.88g/t Au for 28,500 ounces of gold. Mining is scheduled over approximately 11 months, with ore planned to be transported about 236km by road for processing at Forrestania's Edna May facility.
Stage 1 is well advanced toward development, with key mining approvals in place and the remaining Native Vegetation Clearing Permit under assessment. MEGA Resources has been appointed mining contractor and Campbell Gold Haulage engaged to transport ore to Edna May. The PFS schedules project commencement for December 2026.
Project map

Mineral Resource Estimate
Combined JORC Mineral Resource & Stockpile May 2026
| Classification | Au cut-off (g/t) | Tonnes | Grade (g/t Au) | Contained gold (oz) |
|---|---|---|---|---|
| Combine Total | N/A | 2,041,190 | 1.99 | 130,730 |
InSitu JORC Mineral Resource May 2026
| Classification | Au cut-off (g/t) | Tonnes | Grade (g/t Au) | Contained gold (oz) |
|---|---|---|---|---|
| Indicated | 0.5 | 350,920 | 2.91 | 32,820 |
| Inferred | 0.5 | 1,622,580 | 1.84 | 95,760 |
| Total | 0.5 | 1,973,490 | 2.03 | 128,500 |
Stockpile - JORC Mineral Resource May 2026
| Classification | Au cut-off (g/t) | Tonnes | Grade (g/t Au) | Contained gold (oz) |
|---|---|---|---|---|
| Inferred | No Cutoff | 67,700 | 0.99 | 2,150 |
Table 1: JORC MRE March 2026